1. From Workflow to Board
The previous article introduced Jira’s workflow, which defines the rules for how an Issue’s status transitions. A board, by contrast, is the vehicle that visualizes the workflow — showing Issues as cards in different status columns so the team can see the state of the work at a glance.
Jira supports two board modes:
- Scrum board: built for iterative development, with Sprints, a Backlog, and burndown charts
- Kanban board: built for continuous-flow management, emphasizing work-in-progress (WIP) limits
This article focuses on the Scrum board, the most commonly used mode for requirements management.
2. Core Scrum Concepts
Before diving into the board, let’s sort out a few key Scrum concepts:
| Concept | Description |
|---|---|
| Product Backlog | An ordered list of all outstanding work, maintained by the Product Owner |
| Sprint | A fixed time box (usually 1-4 weeks) in which the team commits to finishing a set of work |
| Sprint Backlog | The list of Issues planned for completion in the current Sprint |
| Story Point | A relative estimation unit, used to measure effort rather than time |
| Velocity | The total number of story points the team can complete in each Sprint |
| Sprint Goal | The business objective to be achieved in the current Sprint |
3. Managing the Backlog
The Backlog is the core workspace of requirements management. In Jira’s Backlog view, every Issue that hasn’t entered a Sprint is listed here.
Ordering the Backlog by Priority
The Backlog is not an arbitrary list but a queue ordered by priority:
Backlog(从上到下,优先级递减)
Story: User login feature (P0) ← highest priority
Story: 首页改版(P0)
Story: 搜索功能(P1)
Bug: 修复订单金额计算(P1)
Story: 用户反馈入口(P2)
Story: Data export feature (P3) ← lowest priority
...
Ordering principles:
- P0: core functionality or a blocking problem, must be handled as soon as possible
- P1: important functionality that needs to be finished in the current release
- P2: needed but not urgent
- P3: icing on the cake; do it when there are resources to spare
Jira supports drag-and-drop ordering, so the Product Owner can adjust priorities at any time.
Creating Epics and Stories
In the Backlog, the relationship between Epics and Stories is plainly visible:
Epic: 用户中心改版
├── Story: User registration flow optimization
├── Story: Profile edit page
├── Story: Avatar upload
└── Story: Account security settings
Epic: 数据看板
├── Story: Sales data overview
├── Story: User behavior analysis
└── Story: Report export
The Epic panel helps the team focus on the most important feature modules right now.
4. Sprint Management
Creating a Sprint
Select the Issues you need to finish in this Sprint from the Backlog and drag them into the Sprint area to create a Sprint:
Backlog Sprint 1 (2周, 目标: 用户中心核心功能上线)
───────────────── ─────────────────
Story: 搜索功能 (P1) Story: 用户登录功能 (P0) 5 pts
Story:用户反馈入口 (P2) Story: 首页改版 (P0) 8 pts
... Story: 用户注册流程优化 (P1) 3 pts
Story: 修复订单金额计算 (P1) 2 pts
─────────────────────────────────────
Total: 18 pts (预估速率: 20 pts)
Estimating Story Points
Story points are not man-hours; they measure relative complexity:
- 1 point: a simple change, doable in half an hour
- 3 points: an ordinary feature, half a day to a day
- 5 points: a medium feature, needs 1-2 days
- 8 points: a complex feature, needs 2-3 days
- 13 points: a large feature, needs to be split
A common practice is Planning Poker: team members each give an estimate, and where the estimates diverge widely the team discusses and re-estimates until they converge.
Sprint Capacity Planning
Sprint 容量 = 团队速率 × 可用天数比例
例:团队速率 30 pts/Sprint,本 Sprint 有人休假
可用容量 = 30 × 0.85 = 25 pts
A team using Scrum for the first time has no historical velocity data, so it’s advisable to estimate conservatively for the first 2-3 Sprints and calibrate gradually.
5. The Board View
Once a Sprint begins, the board shows how Issues are distributed across statuses in the form of columns:
┌──────────────────────────────────────────────────────────────────────────────────┐
│ To Do In Progress In Review Testing Done │
├─────────────┬────────────────┬────────────────┬──────────────┬─────────────────┤
│ PROJ-12 │ PROJ-15 │ PROJ-17 │ PROJ-18 │ PROJ-10 │
│ Search │ User login │ Home revamp │ Order bug │ Registration │
│ 5 pts │ 5 pts │ 8 pts │ 2 pts │ 3 pts │
├─────────────┼────────────────┼────────────────┼──────────────┼─────────────────┤
│ PROJ-14 │ PROJ-16 │ │ │ │
│ Dashboard │ Image upload │ │ │ │
│ 3 pts │ 3 pts │ │ │ │
└─────────────┴────────────────┴────────────────┴──────────────┴─────────────────┘
The core value of the board:
- Visualizing bottlenecks: a pile-up in the In Review column means reviews can’t keep up with development
- Spotting blockers: an Issue that sits in one column without moving for a long time needs attention
- The daily standup: the team syncs on progress around the board instead of reporting status
The Daily Standup
The standard standup flow around the board (no more than 1 minute per person):
- What did I do yesterday? (look at the cards in the Done column)
- What am I going to do today? (move cards to In Progress)
- What’s blocking me? (flag the blocker or ask for help)
6. Sprint Reports
Burndown Chart
The burndown chart is the core chart of Sprint management: the horizontal axis is time, the vertical axis is the remaining work:
故事点
│
20│●
│ ●
15│ ●
│ ●
10│ ●
│ ●
5│ ●
│ ●────●
0│____________________________ Time
Day1 Day3 Day5 Day7 Day9
- The actual line below the reference line = ahead of schedule
- The actual line above the reference line = behind schedule, and it needs attention
Sprint Report
After a Sprint ends, Jira generates a report automatically, containing:
- Issues planned for completion vs. issues actually completed
- Issues added / removed
- The completion rate as a percentage
This data feeds the Sprint Retrospective and helps the team improve continuously.
7. Summary
The Scrum board is Jira’s most central requirements-management tool. From ordering the Backlog to Sprint planning, from the daily standup to the Sprint retrospective, Jira provides support for every part of Scrum.
A few practical suggestions:
- Keep grooming the Backlog continuously; don’t wait until a Sprint begins to scramble for a schedule
- Estimate story points together as a team; don’t let one person just call it
- The burndown chart is a reference, not a performance assessment — watch the trend, not the absolute number
Next up, we’ll talk about Jira’s queries and filters — how to quickly find the information you want among a large number of Issues.
A small step forward every day is a new height!